Kyra Court-CR170310
Halie Hernandez
From:Priscilla Martinez
Sent:Tuesday, March 28, 2017 11:18 AM
To:Halie Hernandez
Subject:FW: Kyra Court Daily report
Categories:This message has been archived by Retain on March 28 2017 18:04
From: Halie Hernandez
Sent: Monday, March 13, 2017 11:19 AM
To: Priscilla Martinez <PMartinez@coppelltx.gov>
Subject: FW: Kyra Court Daily report
Halie Hernandez
Administrative Technician
City of Coppell, TX
972-304-3532 (office)
www.coppelltx.gov
From: Matthew Mabry
Sent: Friday, March 10, 2017 2:06 PM
To: Halie Hernandez <HHernandez@coppelltx.gov>
Subject: Kyra Court Daily report
PROJECT Kyra Court
PROJECT NO.
OWNER CITY of COPPELL
CONTRACTOR Haas Rose construction
PROJECT INSPECTOR Matthew Mabry
1
DAILY CONSTRUCTION REPORT
DATE 3-10-2017 REPORT #1
DAY M T W T F S S
Weather:
Temp:
Humidity:
Wind:
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
No work
SIGNATURE
2
PUBLIC WORKS INSPECTOR: MATTHEW MABRY