Prologis Park 121 Northwest Dr--DR170404 DAILY CONSTRUCTION REPORT DATE ___04/04/2017__1:00am_ REPORT #________________ PROJECT: Northwest Dr. DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER Prologis TEMP 85 CONTRACTOR: Mycon WIND S. 27 HUMIDITY 32 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -The contractor poured the first half of the pavement -From the approach to half of Northwest Dr. (South) -I informed Pavecon that they can not spray curing compound all the way across the road because it was too windy -Pavecon had to keep sweeping the road because the concrete trucks kept driving through the mu Pavecon waited until 9:00am to pour because of the muddy condition SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.