Prologis Park-DR170306 (2) DAILY CONSTRUCTION REPORT DATE ___03/06/2017_03:25pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER CITY of COPPELL TEMP 75 CONTRACTOR: CORE WIND S 25 HUMIDITY 53 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Mycon can not set any wall panels today because it is too windy. The contractor is hanging steel for the roof and the wall panels Potter is still setting rebar for the wall panels. They should be complete with pouring the wall panels o Friday SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.