Prologis Park-DR170320
DAILY CONSTRUCTION REPORT
DATE ___03/20/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER Prologis
TEMP 86
WIND S. 19
CONTRACTOR: Mycon
HUMIDITY 35
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Potter is pouring concrete on the north side of the property
-The City of Coppell Police Department assisted in the crane moving across the street to building 6
-Mycon believes they will pour concrete Wednesday and Friday
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.