Prologis Park-DR170323
DAILY CONSTRUCTION REPORT
DATE ___03/23/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER Prologis
TEMP 80
CONTRACTOR: Mycon
WIND S. 36
43
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-I performed a steel inspection the northeast corner of the property
-After the contractor removed the trash debris, I let the contractor know that it was ok to pour the concrete.
-The contractor is still working on the steel for the roof.