Prologis Park-DR170329
DAILY CONSTRUCTION REPORT
DATE ___03/29/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER Prologis
TEMP 75
CONTRACTOR: Mycon
WIND SW 21
HUMIDITY 46
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Steel is still being hung on the building
-Working on the roof of the building
-Patter is grading the next pour on the northeast corner of the property
-Mycon requested a steel inspection for Thursday afternoon
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.