Prologis Park-DR170331 (2)
DAILY CONSTRUCTION REPORT
DATE ___03/31/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER Prologis
TEMP 80
CONTRACTOR: Mycon
WIND S 28
43
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Steel is still being hung on the building
-Working on the roof of the building
-Potter tied the steel for the northeast corner of the building
-I informed the GC that there was too much loose material that needed to be compacted
-I also informed the contractor that there was too much trash and debris
-Some of the rebar lapse were not 24”
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.