Loading...
Prologis Park-DR170331 (2) DAILY CONSTRUCTION REPORT DATE ___03/31/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Partly Cloudy OWNER Prologis TEMP 80 CONTRACTOR: Mycon WIND S 28 43 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -Steel is still being hung on the building -Working on the roof of the building -Potter tied the steel for the northeast corner of the building -I informed the GC that there was too much loose material that needed to be compacted -I also informed the contractor that there was too much trash and debris -Some of the rebar lapse were not 24” SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.