Loading...
Prologis Park-DR170311 DAILY CONSTRUCTION REPORT DATE ___03/11/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER Prologis TEMP 72 CONTRACTOR: Mycon WIND NE 7 HUMIDITY 59% PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -The contractor submitted the revised plans to George and I -No work is being done because of the poor weather. -I informed Mycon that the street needed to be swept because of all of the dirt in the road. SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.