Prologis Park-DR170312
DAILY CONSTRUCTION REPORT
DATE ___03/12/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 74
CONTRACTOR: Mycon
WIND ESE 12
HUMIDITY 64
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Mycon is still working on the interior of the building
-I informed the contractor that Freeport needed to be cleaned
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.