PA1501B-CS170222
DAILY CONSTRUCTION REPORT
DATE ___02/22/2017__________ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER CITY of COPPELL
TEMP 81
WIND S 11 MPH
CONTRACTOR: CORE
HUMIDITY 37
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
Finishing the landscaping
The Electricians on working on the building
The pavement contractor (Miller Sierra) is stripping the forms off of the colored stamped concrete
The pavement contractor is still working on the side walk at the entrance
East
Working on the side walk at the grand pavilion
Using select fill behind the retaining wall
CORE is working on the footing for the performance pavilion
They will be pouring concrete tomorrow at 10:00am
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.