Loading...
PA1501B-CS170222 DAILY CONSTRUCTION REPORT DATE ___02/22/2017__________ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Sunny OWNER CITY of COPPELL TEMP 81 WIND S 11 MPH CONTRACTOR: CORE HUMIDITY 37 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West Finishing the landscaping The Electricians on working on the building The pavement contractor (Miller Sierra) is stripping the forms off of the colored stamped concrete The pavement contractor is still working on the side walk at the entrance East Working on the side walk at the grand pavilion Using select fill behind the retaining wall CORE is working on the footing for the performance pavilion They will be pouring concrete tomorrow at 10:00am SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.