PA1501B-CS170224 DAILY CONSTRUCTION REPORT DATE ___02/24/2017__________ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Sunny OWNER CITY of COPPELL TEMP 59 WIND NW 15 MPH CONTRACTOR: CORE 40 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West Sealed joints in the paving Stripped forms of the approach Called of the traffic control on Saturday The contractor is still working on the irrigation East Core is working on the Performance Pavilion footing Boardwalk backfill of select fill and wall election Performance Pavilion roof framing CORE is working on the Grand Pavilion column masonry CORE is hauling off extra dirt SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.