PA1501B-CS170228
DAILY CONSTRUCTION REPORT
DATE ___02/28/2017__________ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 79
CONTRACTOR: CORE
WIND S 17
HUMIDITY 59
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
The landscapers are installing irrigation
Not much work is being done because of the poor weather today
East
Miller sierra is working on the wall for the board walk.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.