PA1501B-CS170301 DAILY CONSTRUCTION REPORT DATE ___03/01/2017__3:05 pm_ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Mostly Sunny OWNER CITY of COPPELL TEMP 64 CONTRACTOR: CORE WIND N 19 HUMIDITY 13 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West The landscapers are installing irrigation and finishing landscaping The electrician is still pulling the electrical wire to the pavilion East The contractor is still working on framing on the performance pavilion Prepping the retaining wall on the east side of the performance pavilion to be poured Miller Sierra is pouring the retaining wall on the north side of the property CORE is still working on the grand pavilion SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.