Loading...
PA1501B-CS170227 DAILY CONSTRUCTION REPORT DATE ___02/27/2017__________ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Cloudy OWNER CITY of COPPELL TEMP 75 WIND S 15 CONTRACTOR: CORE HUMIDITY 67 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West The landscapers are installing irrigation Plants are being install Not much work is being done because of the poor weather today East Miller sierra is working on the wall for the board walk. Miller Sierra is working on cleaning the entrance I informed the Project Manager the there were complaints on the mud going against the pedestrian walk way SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.