PA1501B-CS170306
DAILY CONSTRUCTION REPORT
DATE ___03/06/2017__3:30pm__ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 75
CONTRACTOR: CORE
WIND S 25
HUMIDITY 53
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
No work was performed today
Had an onsite meeting with Cliff Stephans and Mr. George about the work being done on Saturday
The lane closure should take place at regular working hours.
The work should start on Thursday with Saw cutting
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.