Loading...
PA1501B-CS170310 DAILY CONSTRUCTION REPORT DATE ___03/10/2017____ REPORT #________________ PROJECT: Denton Tap/Sandy Lake DAY M T W T F S S PROJECT NO. WEATHER Overcast OWNER CITY of COPPELL TEMP 56 WIND NNE 9 CONTRACTOR: CORE 79 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: The lettering was being installed on the south monument. I informed the contractor that the traffic control didn’t look correct While the contractor was working on the west monument, I had to inform the contractor to shut down because the traffic control was still wrong and it was almost 3:00pm SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.