PA1501B-CS170309 (2)
DAILY CONSTRUCTION REPORT
DATE ___03/09/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Overcast
OWNER CITY of COPPELL
TEMP 71
WIND S 13 MPH
CONTRACTOR: CORE
73
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
The landscapers are installing irrigation and finishing landscaping
The architect and the engineer is performing their walk-thru today
East
Miller Sierra is pouring the sidewalk on the north side of the property to connect the 2 existing sidewalks
The contractor is still working on installing brick on the pavilion and working on the roof
Core is preparing to backfill the retaining wall
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.