PA1501B-CS170310 (2) DAILY CONSTRUCTION REPORT DATE ___03/010/2017___ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Overcast OWNER CITY of COPPELL TEMP 66 WIND NNE 9 CONTRACTOR: CORE 79 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West The landscapers are installing irrigation and finishing landscaping The architect and the engineer has already performed walk-thru for the project East The contractor is backfilling the retaining wall on the retaining wall at the bridge. CORE is still backfilling the retaining wall at the performance pavilion SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.