PA1501B-CS170320
DAILY CONSTRUCTION REPORT
DATE ___03/20/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER CITY of COPPELL
TEMP 86
WIND S. 19
CONTRACTOR: CORE
HUMIDITY 35
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
-Core is installing sealant to the sidewalk and to the parking area
-Mowing grass by the houses
-Finishing the soft trail on the north side of the property
East
-Hauling stock piled dirt off the property
-Installing bricks on Grand Pavilion column and walls
-Bricks at Boardwalk pavilion
-Roofing on the performance pavilion
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.