PA1501B-CS170322 DAILY CONSTRUCTION REPORT DATE ___03/22/2017___ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER CITY of COPPELL TEMP 81 CONTRACTOR: CORE WIND SSE 13 HUMIDITY 57 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West -Miller Sierra is working on cleaning and sealing all of the saw-cut, expansion joints and cracks in the pavement -The stripping should be in on Thursday -The punchlist should be complete on Saturday -Walk-Thru is scheduled for Monday at 9:00am East -Core is working on the bridge -Brick is being done on all of the pavilion -ONCORE is onsite today inspecting the broken line SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.