CONSTRUCTION ACTIVITIES:
West
-Miller Sierra is working on cleaning and sealing all of the saw-cut, expansion joints and cracks in the pavement
-The stripping should be in on Thursday
-The punchlist should be complete on Saturday
-Walk-Thru is scheduled for Monday at 9:00am
East
-Core is working on the bridge
-Brick is being done on all of the pavilion
-ONCORE is onsite today inspecting the broken line