PA1501B-CS170323
DAILY CONSTRUCTION REPORT
DATE ___03/23/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER CITY of COPPELL
TEMP 80
CONTRACTOR: CORE
WIND S. 36
43
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
-Miller Sierra is working on cleaning and sealing all of the saw-cut, expansion joints and cracks in the pavement
-No stripping was completed today, Strippers will be onsite tomorrow
-The punchlist should be complete on Saturday
-Walk-Thru is scheduled for Monday at 9:00am
East
-Core is working on the bridge
-Brick is being done on all of the pavilion
-ONCORE connected the broken line at night
-The CORE is still running on the generator
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.