Loading...
PA1501B-CS170323 DAILY CONSTRUCTION REPORT DATE ___03/23/2017___ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Partly Cloudy OWNER CITY of COPPELL TEMP 80 CONTRACTOR: CORE WIND S. 36 43 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West -Miller Sierra is working on cleaning and sealing all of the saw-cut, expansion joints and cracks in the pavement -No stripping was completed today, Strippers will be onsite tomorrow -The punchlist should be complete on Saturday -Walk-Thru is scheduled for Monday at 9:00am East -Core is working on the bridge -Brick is being done on all of the pavilion -ONCORE connected the broken line at night -The CORE is still running on the generator SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.