Prologis Park 121 Northwest Dr--DR170316 DAILY CONSTRUCTION REPORT DATE ___03/16/2017__11:00am_ REPORT #________________ PROJECT: Northwest Dr. DAY M T W T F S S PROJECT NO. WEATHER Cloudy OWNER Prologis TEMP 60 WIND S 14 CONTRACTOR: Mycon HUMIDITY 85 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -There was an irrigation line broke on Northwest Dr (North) -I informed Chance from Mycon that the line needed to be repaired and that the irrigation line will need a casing on it -Pavecon is working on Northwest Dr. (South) -Pavecon plans to pour all of the pavement on both drives on the 27th -I informed the contractor to turn all the signs around for lane closures that they are not using SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.