Prologis Park 121 Northwest Dr--DR170317
DAILY CONSTRUCTION REPORT
DATE ___03/17/2017__1:00am_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 73
CONTRACTOR: Mycon
WIND S 22
60
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-No work is being done on Northwest Dr. (North)
-Mycon has the approval from Prologis to go ahead and put the sleeve in under the concrete where the irrigation line is
-Pavecon is still working on the subgrade for the south side of the property.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.