Prologis Park 121 Northwest Dr--DR170314 (2) DAILY CONSTRUCTION REPORT DATE ___03/14/2017_03:45pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Mostly Sunny OWNER CITY of COPPELL TEMP 59 CONTRACTOR: CORE WIND SSE 6 HUMIDITY 32 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Mycon is hanging wall panels Potter should be finished pouring wall panels by the end of the week SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.