Prologis Park 121 Northwest Dr--DR170317 (2)
DAILY CONSTRUCTION REPORT
DATE ___03/17/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 73
CONTRACTOR: Mycon
WIND S. 22
60
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
No panels are being hung today because it’s too windy
I informed Chet that the plans call for the header to be installed so they will be in by Monday
I inspected the steel in the parking area
Potter should be pouring concrete on Monday at 7:00am
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.