Prologis Park 121 Northwest Dr--DR170320
DAILY CONSTRUCTION REPORT
DATE ___03/20/2017__1:00am_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER Prologis
TEMP 86
WIND S. 19
CONTRACTOR: Mycon
HUMIDITY 35
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Installed the slip line for the paving machine
-Mycon plans to flush the water line tomorrow or Wednesday
-Pavecon will set forms for the pavement
-Mycon will have their landscapers install the casing for the water line
-I informed the contractor it was ok to trench the line and compact it back in.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.