Prologis Park 121 Northwest Dr--DR170322
DAILY CONSTRUCTION REPORT
DATE ___03/22/2017__1:00am_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 81
CONTRACTOR: Mycon
WIND SSE 13
51
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-I informed Chance that the water line may need to be Bac-T
-I informed Eric Terry that the sewer line needed to monolithic
-Eric said that he will check all the manhole elevations. They will block out any manholes that need to be changed.
-Jose will be onsite tomorrow to flush the water line
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.