Prologis Park 121 Northwest Dr--DR170327
DAILY CONSTRUCTION REPORT
DATE ___03/27/2017__1:00am_ REPORT #________________
PROJECT: Northwest Dr.
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 65
CONTRACTOR: Mycon
WIND N. 9
HUMIDITY 65
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Pavecon finished tying the steel for Northwest Dr.
-Pavecon tied set-up the machine and pre-ran the machine to make sure that it ran properly
-I inspected the steel spacing and depth
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.