PA1501B-CS170331 DAILY CONSTRUCTION REPORT DATE ___03/31/2017___ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Partly Cloudy OWNER CITY of COPPELL TEMP 80 CONTRACTOR: CORE WIND S 28 43 HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West -We performed a final walk-thru -Everything was completed by the end of the day, except for one marking on the curb for the manhole -I checked the flapper for the storm drain East -CORE is still working on the pavilions roofs and brick siding -CORE is still working on the bridge I informed the plumber that the we could not use pipe glue or soder the pipe on the copper SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.