PA1501B-CS170403
DAILY CONSTRUCTION REPORT
DATE ___04/03/2017___ REPORT #________________
PROJECT: Andrew Brown
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER CITY of COPPELL
TEMP 72
WIND SW 4
CONTRACTOR: CORE
HUMIDITY 48
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
West
-The striping crew is installing the fire lane paint
-Tim Oats said that it was ok for the paint to not be on the
Eastcurb
-CORE is still working on the pavilions roofs and brick siding
-CORE is still working on the bridge
-I informed the plumber that the we could not use pipe glue or soder the pipe on the copper
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.