CRDC1401-DR170404
DAILY CONSTRUCTION REPORT
DATE ___04/04/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 85
CONTRACTOR: Pavecon
WIND S. 27
HUMIDITY 32
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-I took pictures of all of the damaged landscaping
-I spoke to John Elias to ask if he had any pictures and he informed me that they didn’t take any pictures and that most of the landscaping was
repaired since the walk through
-I reminded Mike that the street name signs needed to be removed
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.