CRDC1401-DR170406
DAILY CONSTRUCTION REPORT
DATE ___04/06/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER CITY of COPPELL
TEMP 74
CONTRACTOR: Pavecon
WIND NW 6
30
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-I informed Michael B. that the large pipe was still at 123 E. Sandy Lake
-The lights are working over the street signs now
-Michael said that he will take care of the dirt pile in the road
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.