CRDC1401-DR170329
DAILY CONSTRUCTION REPORT
DATE ___03/29/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER CITY of COPPELL
TEMP 75
CONTRACTOR: Pavecon
WIND SW 21
HUMIDITY 46
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-We had another weekly meeting
-Michael B. from Pavecon went over some of the items on the change order
-ATCI is working on the ridge pipe under the bridge in front of Andrew Brown West
-Texas Bominite will be on site tomorrow to work on the last few areas
-Pavecon will have a crew onsite tomorrow to strip the plastic and seal the expansion joints
-I emailed Frontier about the services on the pole behind Chipotles
-I got an email from the Richard Brewster stating that the holes at the boxes by 7-11 and Scholzsky’s were not theirs.
-George emailed a Frontier rep to see if the line was theirs
SIGNATURE