CRDC1401-DR170330
DAILY CONSTRUCTION REPORT
DATE ___03/30/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Partly
Cloudy
OWNER CITY of COPPELL
TEMP 63
CONTRACTOR: Pavecon
WIND WNW 17
46
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-I checked the pipe under the bridge
-Pavecon start removing the plastic on the expansion joints and sealing them
-AALC is still working on the landscaping
SIGNATURE
PUBLIC WORKS INSPECTOR