CRDC1401-DR170228
DAILY CONSTRUCTION REPORT
DATE ___02/28/2017__________ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER CITY of COPPELL
TEMP 79
CONTRACTOR: CORE
WIND S 17
HUMIDITY 59
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
No work was performed today
I text Mike B. that we needed more information on the electrical box on the monument before we make a descision on the whether the electrical
box is moved on the outside of the monuments.
SIGNATURE
PUBLIC WORKS INSPECTOR