CRDC1401-DR170303
DAILY CONSTRUCTION REPORT
DATE ___03/03/2017__________ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Cloudy
OWNER CITY of COPPELL
TEMP 69
WIND S 17
CONTRACTOR: CORE
88
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
No work was performed today
Scott and I met with the owner of The Learning Experience and informed him of the work that’s going to take place in front of his building.
We informed the owner that the road in front of his business will be would be shut down for a couple days and that the parents and employees
would have to make u-turn to get to his building.
We will provide the drawing and write an email for the owner to hand out to the parents and the other employees
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.