Prologis Park-DR170320 (2)
DAILY CONSTRUCTION REPORT
DATE ___03/20/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Cloudy
OWNER Prologis
TEMP 82
CONTRACTOR: Mycon
WIND S 12
HUMIDITY 59
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-CalHar is still working on the manhole adjustment
Mycon repaired the broken silt fence.
-Mycon is still working on the interior of the building
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.