CONSTRUCTION ACTIVITIES:
-Pavecon is grading the sidewalks on Northwest Dr. south
-Pavecon is grading and forming sidewalk on Northwest Dr. North
-CalHar is wrapping all of the inlets with silt material.
-Pavecon plans to pour concrete on the sidewalk on Monday
SIGNATURE
PUBLIC WORKS INSPECTOR