PA1501B-CS170419 DAILY CONSTRUCTION REPORT DATE ___04/19/2017___ REPORT #________________ PROJECT: Andrew Brown DAY M T W T F S S PROJECT NO. WEATHER Cloudy OWNER CITY of COPPELL TEMP 72 WIND S 13 CONTRACTOR: CORE HUMIDITY 77 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: West -The contractor is still working on the landscaping East -CORE is cleaning the streets -Working on water line around the park -I informed the plumber again that we can’t use pipe dope and Teflon on the meters -Miller Sierra plans to pour concrete on the east pavilion and over both bridges -I informed Miller Sierra that the mud needed to be removed prior to pouring the walking area near the pavilion SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.