Kyra Court-CS170510 (2)
Halie Hernandez
From:Matthew Mabry
Sent:Thursday, May 11, 2017 3:58 PM
To:Halie Hernandez
Subject:Kyra court Walkthru - Sewer complete SS-INSP-05-2017-002988
Categories:This message has been archived by Retain on May 11 2017 17:47
Matthew Mabry
Engineering Construction Inspector
City of Coppell, TX
214-406-5223 (cell)
www.coppelltx.gov
From: ITsupport@coppelltx.gov \[mailto:ITsupport@coppelltx.gov\]
Sent: Thursday, May 11, 2017 8:25 AM
To: Debbie Taber <dtaber@coppelltx.gov>; Kori Konon <KKonon@coppelltx.gov>; Matthew Mabry
<MMabry@coppelltx.gov>; Marcus Marion <MMarion@coppelltx.gov>; Darryl Zbranek <dzbranek@coppelltx.gov>
Subject: Walkthru - Sewer complete SS-INSP-05-2017-002988
Sewer Walkthru has been completed: SS-INSP-05-2017-002988
Meet at 8:30 AM on 05/10/2017 per Matthew Mabry at 214-406-5223 with the Engineering Department for a
Final Walkthrough
Location: Kyra Court
Note: follow up walk thru on kyra ct for sewer is passed.
Dan Dimafelix
Billy Williams