CRDC1401-DR170502
DAILY CONSTRUCTION REPORT
DATE ___05/02/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Sunny
OWNER CITY of COPPELL
TEMP 86
CONTRACTOR: Pavecon
WIND SSE 10
HUMIDITY 30
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Mike B from Pavecon had a meeting with the irrigator.
-The irrigation was turned back on and there were no signs of leakage
-Mike informed thee owner that their irrigation was turned on
-Pause removed the electrical meter box. They will get the meter box to Cody
-Pause filled the holes that were left from ONCORE
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.