Loading...
CRDC1401-DR170502 DAILY CONSTRUCTION REPORT DATE ___05/02/2017____ REPORT #________________ PROJECT: Denton Tap/Sandy Lake DAY M T W T F S S PROJECT NO. WEATHER Mostly Sunny OWNER CITY of COPPELL TEMP 86 CONTRACTOR: Pavecon WIND SSE 10 HUMIDITY 30 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -Mike B from Pavecon had a meeting with the irrigator. -The irrigation was turned back on and there were no signs of leakage -Mike informed thee owner that their irrigation was turned on -Pause removed the electrical meter box. They will get the meter box to Cody -Pause filled the holes that were left from ONCORE SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.