CRDC1401-DR170425
DAILY CONSTRUCTION REPORT
DATE ___04/25/2017____ REPORT #________________
PROJECT: Denton Tap/Sandy Lake
DAY
M T W T F S S
PROJECT NO.
WEATHER Party
Cloudy
OWNER CITY of COPPELL
TEMP 83
CONTRACTOR: Pavecon
WIND S. 24
HUMIDITY 60
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-ATCI is working why the lights on Sandy Lake will not go off
-Pause is onsite and they are backfilling the open holes
-Pause will be removing the box and the meter box in front of Frost Bank
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.