Prologis Park-DR170326
DAILY CONSTRUCTION REPORT
DATE ___03/26/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Overcast
OWNER Prologis
TEMP 63
WIND NW 24
CONTRACTOR: Mycon
HUMIDITY 78
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Mycon is grading the far east side of the property
-All of the erosion control on the east side of the property has been repaired
-Mycon is still working on the exterior and the interior of the property
-Mycon is still pouring pavement in between the floor and the wall.
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.