Prologis Park-DR170327
DAILY CONSTRUCTION REPORT
DATE ___03/27/2017_12:30pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Sunny
OWNER Prologis
TEMP 73
WIND SE 19
CONTRACTOR: Mycon
HUMIDITY 40%
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
-Mycon is still working on the exterior of the property
-Potter is working on the finishing the steel tying
-I informed Potter that the manholes needed to be tied at an angle
-The far north side of the property needed to be either compacted or the loose rocks needed to be removed
-Some of the areas needed lime added to it because of the rain
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.
DAILY CONSTRUCTION REPORT
REPORT #_____________
Page _____ of _____ pages.