Prologis Park-DR170326 (2) DAILY CONSTRUCTION REPORT DATE ___03/26/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Mostly Cloudy OWNER Prologis TEMP 83 CONTRACTOR: Mycon WIND SSE 16 60% HUMIDITY PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -Potter is pouring concrete on the far east side of the property -Mycon is still working on the interior of the building -I inspected the steel again and Potter made all of the corrections that I need done SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.