Prologis Park-DR170509 DAILY CONSTRUCTION REPORT DATE ___05/09/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Cloudy OWNER Prologis TEMP 82 WIND SSE 10 CONTRACTOR: Mycon HUMIDITY 57 PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -Mycon is still grading the east side of the property -Concrete is being pour between the walls and the floor of the building -I will perform a rebar inspection tomorrow depending on the weather SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.