Prologis Park-DR170510 DAILY CONSTRUCTION REPORT DATE ___05/10/2017_12:30pm__ REPORT #________________ PROJECT: Building 3 DAY M T W T F S S PROJECT NO. WEATHER Cloudy OWNER Prologis TEMP 73 WIND SE 13 CONTRACTOR: Mycon HUMIDITY 81% PROJECT INSPECTOR: Marcus Marion AVERAGE FIELD FORCE NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: -The contractor is still grading -I performed a rebar inspection this afternoon. I informed the contractor that the loose debris needed to be removed and the rocks needed to be taken out -Mycon is not responsible for the broken water line SIGNATURE PUBLIC WORKS INSPECTOR Page _____ of _____ pages. DAILY CONSTRUCTION REPORT REPORT #_____________ Page _____ of _____ pages.