Fairfield Inn-CR170516
Halie Hernandez
From:Matthew Mabry
Sent:Wednesday, May 17, 2017 2:23 PM
To:Halie Hernandez
Subject:Fairfield Inn daily report for 5-16-17
Date: 5-16-17
Weather: sunny
Project Contact: James Anderson 214-600-3828
Contractor: Northpoint Construction
Construction Activities Performed: 8 am rebar inspection. Used laser level to make sure they were compliant.
Everything looked fine
Construction Activities Planned: Today they plan on finishing placement of rebar. Have requested an 8 am inspection
for tomorrow
Construction issues: Some SWP3 issues along 121 service road.
As Built Items:
Installed irrigation meter from existing ARV. Jerry Davis approved this.
Changed sidewalk along 121 because of existing hydrant
Report Completed By: Matthew Mabry