Fairfield Inn-CR170515 Halie Hernandez From:Matthew Mabry Sent:Wednesday, May 17, 2017 10:08 AM To:Halie Hernandez Subject:Fairfield Inn and suites daily report 5-15-17 Date: 5-15-17 Weather: sunny Project Contact: James Anderson 214-600-3828 Contractor: Northpoint Construction Construction Activities Performed: Rebar placement for sidewalk around the property Construction Activities Planned: Today they plan on finishing placement of rebar. Have requested an 8 am inspection for tomorrow Construction issues: Some SWP3 issues along 121 service road. As Built Items: Installed irrigation meter from existing ARV. Jerry Davis approved this. Changed sidewalk along 121 because of existing hydrant Report Completed By: Matthew Mabry 1