DAILY CONSTRUCTION REPORT
DATE ___03/03/2017_03:25pm__ REPORT #________________
PROJECT: Building 3
DAY
M T W T F S S
PROJECT NO.
WEATHER Mostly
Sunny
OWNER CITY of COPPELL
TEMP 64
CONTRACTOR: CORE
WIND N 19
13
HUMIDITY
PROJECT INSPECTOR: Marcus Marion
AVERAGE FIELD FORCE
NAME OF CONTRACTOR NON-MANUAL MANUAL REMARKS
VISITORS
TIME REPRESENTATIVE REPRESENTING REMARKS
EQUIPMENT AT THE SITE:
CONSTRUCTION ACTIVITIES:
Mycon is still working on hanging wall panel
Mycon is also working on connecting the steel to the wall panels
Potter is still working on pouring wall panels
SIGNATURE
PUBLIC WORKS INSPECTOR
Page _____ of _____ pages.